CONSTRUCTION BID RESULTS
Tabulation of Bids Opened on March 27, 2007
Project: Job 07-017 Aiea Gulch Well MCC Replacement
Contact: Albert Mau
@ (808) 748-5137
|
CONTRACTOR |
AMOUNT |
|
|
|
|
FOPCO,
Inc. |
$519,225.00 |
|
American
Piping & Boiler Co. |
$611,117.00 |
|
VT
Griffin |
$628,299.41 |
|
Fordable
Construction LLC |
$659,000.00 |
|
Elite
Pacific Construction, Inc. |
$660,000.00 |
|
Ralph S.
Inouye Co. Ltd. |
$772,200.00 |
|
|
|
|
Sub-contractors: |
|
|
T & M
Construction Services, Inc., C-26483, Electrical |
|
|
Unitek
Insulation, LLC, C-11851, Hazardous Material Removal & Disposal |
|
|
Akira
Yamamoto Painting, Inc., C-04970, Painting |
|
NOTE: These figures are preliminary or apparent
bid results of the date of bid opening.
All bids are subject to evaluation.